In the course of the development of slag vertical mill, has been more people know and well-known, and with the development of industrialization, the application is also more and more common, the use of cement mill more and more users, the following state industry Technology Group for everyone to introduce cement mill test considerations.

Vertical mill working process

1, no-load running test machine, before no-load test machine, the roller device should be firmly rolled with wire ropes to avoid contact with the grinding roller and the ring impact, and then stand the main engine air to run the test machine for not less than 1 hour ; The host should be smooth operation, the tank oil temperature shall not exceed 80 ℃, the temperature does not exceed 40 ℃. Host and analyzer rotation direction shown in Figure 4.

2, the blower should be no-load boot, to be loaded after normal operation, and then observe the smooth operation, no abnormal noise and vibration, rolling bearing temperature shall not exceed 70 ℃, the temperature rise shall not exceed 35 ℃.

3, the load test machine running time of not less than 8 hours after the cement mill normal work no abnormal noise machine, the pipe joints without leakage phenomenon, the test again after the tightening of the fastening body, you can put into normal use.

Vertical mill working process

CHAENG(Great Wall Machinery Co.,Ltd) main products:Turnkey Cement Plant, GGBS Plant,Rotary Kiln,Vertical Roller Mill, Ball Mill, Rotary dryer, Custom Steel Castings,impact crusher, jaw crusher, hammer crusher and so on.We are professional slag powder/cement equipment manufacturer, so we can build slag powder /cement plant for you.